Monday, 7 April 2014

Maintenance List - The Continuing Adventure



Since Johnathan and I moved Fluenta from Mazaltan to La Cruz we have been busy …  A data dump from my maintenance spreadsheet below.  I deleted most of the reoccurring items like battery water, zinc replacement, cleaning etc.

Some of these I did myself, some were contracted and my father-in-law helped me with a whole lot of this.  Funny to see the list now as some of the items are a few hours work and some like the solar panel array and the new autopilot took several days each.

A few photos at the end of the list

Wendall and Benjamin showing off the cargo net Wendall designed and made for "Trickle" the Fatty Knees sailing dingy


Aft head leak
12V plugs in cockpit
Autopilot Remote
Adjust furlboom mandrel
Adjust top of furler - chafing on genoa halyard
Aft Cabin Hatch
Aft head leak
Aft head vented loops
AIS antenna
AIS Splitter power from AIS cct breaker
AIS to chartplotter
autopilot autotune
Autopilot crossbar - new
Autopilot R3000X
Backstay – service hydraulics (Contract)
Battery water - vent caps
Better bilge pump system. With panel switch and alarm, y-valve
Better grey water system
Bilge clean - flush bilge and clean bilge compartments
Bow running light fixture replacement
Bulbs for engine panel
Calibrate BTW
Chain replacement
change water filter - pressure water
clean manual bilge pump strum box
Clean reefer condenser
Cockpit mike
cover for anchor windlass (Contract)
Dripping foot pump taps
Dripping tap in aft head
Engine zincs x 2
Enlarge rudder stop
Fabric cover for mast boot (Contract)
Fix bookcase hinge
Fix reefer pressure switch
Fix stbd cubby door
Flush water tanks
Fresh water fwd tank valve leak
Fwd head and reinstall shelves for fwd head
Fwd Head Hatch repair
Galley fan
Genoa refurb - loose threads, repair PV sailing repair (Contract)
Grease rudder reference bearing
hdg input to ais
Hyd panel - service (Contract)
Impellor leak and replacement
Install Chartplotter
Jacklines –new
Jib halyard pennant - amsteel lashing
Kayak repair
Knife in anchor locker
Lazerette Access - wood screws
Leaking water manifold
longer mainsheet
main - batten pockets, clew and tack rings (Contract)
Main - re-tie tack and clew line - with tubular webbing for tack/clew ring and ferule eye strap and back up clew line to back of mandrel
main furler/main halyard  block - rebuild
mainfurl - Grease the grease nipple on the aft end of the spar.
mainsail - telltales
Mark halyard with whipping
Mastboot - install
mastboot - hose clamps
modify lazerette floor board - more space for rudder shaft
move GPS antenna
Move pinstop staysail car in front of genoa lead car
new autopilot
new reefer cooling water filter
non return valve - bilge pump
Oil (100 hrs) - done at 4276.5
Overhaul winch – Anderson
Overhaul winch - port 23
Overhaul winch - port 27 Halyard
Overhaul winch - port 28
Overhaul winch - port 36
Overhaul winch - stbd 27 main sheet
Overhaul winch - stbd 27 outboard
Overhaul winch - stbd 28
Overhaul winch - stbd 36
Paint touch up – hull (Contract)
PFD CO2/bobbins replace
pin shackle for boom lift
pin shackle for staysail
plug gap aft of mast – silicone
portable watermaker – annual maintenance
preventer setup - 2x amsteel with eyes/thimbles, existing preventer double braid with soft shackle, 4x snatch blocks
Prop/shaft zincs
PVC tube on fwd lower shrouds
Rebed pad eye in aft cabin stbd cupboard
rebed slider for cockpit hatch
Red LED in aft cabin
redo network power connection
Reefer - adjust high pressure switch - 170 psi
repair dodger frame
replace bilge pump hose - remove kink
replace CO sensor
Replace dingy davit line
replace mainsail tack and clew lines
replacement autopilot drive
Reseize and seize shackles throughout
rig tuning
rope clutch clean
salt water tap leak
service bilge manual pump - sand, paint interior, new valves
Setscrew in forestay
sextant alignment
sheave replacement for spin pole topping lift
Sheet bags (genoa x2 plus mast) with mesh (Contract)
Smoke alarm batteries
soft shackle for spin tack
Solar panel - rail mount install
Solar panel install - Dodger
solas tape for reef marks and tape around head ring
solas tape on rail mount solar panels
Spartite
Spectra loops for running backstays
spin halyards, sheets - doughnut and tape
Spinnaker Halyard replacement
SSB GTO15 wire
SSB KISS Counterpoise
Stanchion rebed - saloon fwd stbd side
Stanchion repair (Contract)
start battery replacement
Staysail - pennant, hanks, bag
Stbd aft cabin fan
Steaming light bulb
sun cover for front of main sail (Contract)
Tach bulb
TDS - around deck flange and heater exhaust
telltale on spin pole
Test manual bilge pump
Touch up engine paint
traveller - shackle replacement
Trickle cover (Contract)
Trickle mast cover
Trickle rudder repair
Trickle/RHIB Storage
vang line - double block
Vang repair - gas cylinder
Vang repair - new line
Vented loops - engine
Vents for battery box
water tank flush
watermaker - 12v fan
Watermaker - carbon filter
Watermaker - elbow
Watermaker – membrane
Watermaker - new feed pump
Watermaker - pleated filter
watermaker leak
white fiberglass paint touch up (stbd side near drain, port side of cockpit)
Wifi GoFree -
Windlass - bimonthly

Windlass Service - preseason service
Window leak - fwd stbd
Yellow tape on hawespipe hole

Johnathan helping me raise the genoa after we added a pendant

My Father-in-Law, Wendall, showing off our new solar panels.  Note oil and distilled water  (for the batteries) on deck getting ready to be stowed for the passage.

My dad helping me attach the clew to the furler

Yet more work on the refrigeration

No comments:

Post a Comment

Comments ? (Note all comments are moderated)